I'm using Project Server 2003 with MS Project 2003, SharePoint (2.0?), SQL
2000. Server is Windows 2003, my client is XP Pro sp2+.
We have multiple projects with resources working on more than one project.
I am trying to determine who has missing time entry, so I opened all
projects and looked at the Resource Usage sheet to see whose Actuals didn't
total to 8 hours a day.
When I compare this to the PWA Resource "Adjust Actuals" view, I don't see
the same numbers. I've tried synching to protected actuals, but that
doesn't solve the problem. Am I looking in the wrong place in MS Project?
Any other thoughts on what might be the issue?
2000. Server is Windows 2003, my client is XP Pro sp2+.
We have multiple projects with resources working on more than one project.
I am trying to determine who has missing time entry, so I opened all
projects and looked at the Resource Usage sheet to see whose Actuals didn't
total to 8 hours a day.
When I compare this to the PWA Resource "Adjust Actuals" view, I don't see
the same numbers. I've tried synching to protected actuals, but that
doesn't solve the problem. Am I looking in the wrong place in MS Project?
Any other thoughts on what might be the issue?