Added Labor Day holiday to calendar and work is still showing as s

P

Paul

After I'd entered everything, someone pointed out to me that there was a
compan-wide holiday in the schedule. I changed the Calendar show this, and
indeed that Monday is now grayed out on the Gantt -- but work is still shown
as occuring on that day. For example: "Contractor Orientation" is still shown
to start and stop on that day.

Shouldn't all tasks have updated to skip that workday and push off Start
ASAP" to the next available work day ??
 
P

Paul

Scheduling ignores resource calendars check box on the Advanced tab in the
Task Information dialog box is NOT selected, either.
 
S

Steve House [Project MVP]

Is recalculate set to "automatlc?" (Tools, Options, Calculation) Which
calendar did you post the holiday in and are you sure it's the one governing
to tasks in question? Are you sure work is still scheduled on the holiday
or is it just that the Gantt bars are crossing over it? ( If I have a task
that starts on Thursday and ends the following Tuesday, its bar will cross
the weekend even though there's no work taking place on Sat or Sun.) When
you entered task durations, did you use elapsed time - ie, the duration is
"2ed" instead of "2d"? Elapsed time ignores working time and non-working
time distinctions.
 