After I'd entered everything, someone pointed out to me that there was a
compan-wide holiday in the schedule. I changed the Calendar show this, and
indeed that Monday is now grayed out on the Gantt -- but work is still shown
as occuring on that day. For example: "Contractor Orientation" is still shown
to start and stop on that day.
Shouldn't all tasks have updated to skip that workday and push off Start
ASAP" to the next available work day ??