B
BG_SAABer
Today quiz is related to MS Project 2003. Problem is simple.
Let's say we have 1000$ budget for security protection.
Let's say we rented a castle for 1 month.
Let's say regular cost for guardsman is 10$/hour.
What I like to do is to create a single task that will have a fixe
start date and fixed end date (duration of 30 calendar days will b
enclosed between start and end date), where a single resource will b
allocated, with cost of resource to be 10$/hour, so that the total Cos
to be exactly 1000$. The only flexible components we have is hours pe
day worked. So what I like Project to calculate for me is what my
allocation is suppose to be to match these numbers. In other words, ho
many hours per day I have to work so that end up spending 1000$ wit
rate of 10$/hour over 30 calendar days? Project has integer numbe
increment and does not accept values with fractional. So if I like t
assign a resource with 3.75%, Project 2003 rejects the fraction an
rounds.
One might say the answer is 3.33h/day. However I can not find an
combination of settings that will enable me to fix the start day, en
day, total work/cost, and use a resource with fixed hourly rate.
always get start and end day that I do not like, or my total work valu
gets out of control. Work hours for the entire task is what I associate
with Cost. Since Cost is not directly changeable, only work can b
manipulated. In our case the work is 100 hours.
What could be the solution
Let's say we have 1000$ budget for security protection.
Let's say we rented a castle for 1 month.
Let's say regular cost for guardsman is 10$/hour.
What I like to do is to create a single task that will have a fixe
start date and fixed end date (duration of 30 calendar days will b
enclosed between start and end date), where a single resource will b
allocated, with cost of resource to be 10$/hour, so that the total Cos
to be exactly 1000$. The only flexible components we have is hours pe
day worked. So what I like Project to calculate for me is what my
allocation is suppose to be to match these numbers. In other words, ho
many hours per day I have to work so that end up spending 1000$ wit
rate of 10$/hour over 30 calendar days? Project has integer numbe
increment and does not accept values with fractional. So if I like t
assign a resource with 3.75%, Project 2003 rejects the fraction an
rounds.
One might say the answer is 3.33h/day. However I can not find an
combination of settings that will enable me to fix the start day, en
day, total work/cost, and use a resource with fixed hourly rate.
always get start and end day that I do not like, or my total work valu
gets out of control. Work hours for the entire task is what I associate
with Cost. Since Cost is not directly changeable, only work can b
manipulated. In our case the work is 100 hours.
What could be the solution