Adding a task view

R

Ryan

How do I add a Task Field (ie: Text1) as a column in the Resource Usage View
and keep the data in? I want to see the value from the Gantt Chart as a
column in Resource Usage View.

Ryan
 
R

Rob Schneider

Ryan,

Short answer is that you can't as there is no logical connection to do
so. Task fields are task fields. Resource fields are Resource fields.
They aren't related except that they are link by 1 to many resources
are assigned to individual tasks.
 
J

John

Ryan said:
How do I add a Task Field (ie: Text1) as a column in the Resource Usage View
and keep the data in? I want to see the value from the Gantt Chart as a
column in Resource Usage View.

Ryan

Ryan,
First you need to go to our MVP website at:
http://www.mvps.org/project/faqs.htm
and read FAQ 51 - Data Types: Task, Resource, and Assignment. Then you
might want to check out FAQ 37 - Custom fields in tables. Then if you
still have a question, repost.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top