I created a project/resource calendar for first and second shifts.
Now I want to add Saturday to the work schedule and when doing this I
get a message that says:

"The argument value is not valid. Verify that the value is spelled
correctly, and that it is the type that this argument expects."

All I am doing is selecting the Saturday column and choosing the Non
default working time that has been applied to the other days of the
week already.

Why am I getting this error?
 
J

Jan De Messemaeker

Hi,

As the way to do this changed fundamentally from 2003 to 2007, it is
interesting to know which version you are referring to.
Greetings,
 
C

ctank228

Hi,

As the way to do this changed fundamentally from 2003 to 2007, it is
interesting to know which version you are referring to.
Greetings,

--
Jan De Messemaeker








- Show quoted text -

MS Project 2003
 
J

Jan De Messemaeker

Hi,

Never seen this, especially not in 2003.
Can yoiu send me the file, I'll have a look.
jandemetATprom-ade.be
Replace ATby @

Greetings,
 

Ask a Question