So here is what I am trying to do:
We have a task Fab1 that has to be done before Test1 can begin.
Test1 has predecessors TestP1, TestP2, TestP3, TestP4. That all have
a path to Test1 as there successor.
If I schedule Test1 ASAP and all the TestPs ALAP, they should all bump
up against Test1's start which is driven by the Completion of Fab1.
This is a typical Fab & Test cycle, where a number of meetings, plans,
etc need to be done before product received. There is no relationship
to Fab1 and the TestPs.
This would have worked fine using Primavera, is this another Project
quirk ??
We have a task Fab1 that has to be done before Test1 can begin.
Test1 has predecessors TestP1, TestP2, TestP3, TestP4. That all have
a path to Test1 as there successor.
If I schedule Test1 ASAP and all the TestPs ALAP, they should all bump
up against Test1's start which is driven by the Completion of Fab1.
This is a typical Fab & Test cycle, where a number of meetings, plans,
etc need to be done before product received. There is no relationship
to Fab1 and the TestPs.
This would have worked fine using Primavera, is this another Project
quirk ??