D
dalbaugh
just upgraded to 2002 from 2000. I could reschedule uncompleted work and my
hours and dates would roll to the updated date. Now 2002 is telling me that
it will not reschedule my tasks because of constrainst. I schedule by finish
date and use the ALAP constraint for all activities. When I try and use the
ASAP constraint on them and then reschedule - it still will not roll the
dates as before. Is there an easy solution?
hours and dates would roll to the updated date. Now 2002 is telling me that
it will not reschedule my tasks because of constrainst. I schedule by finish
date and use the ALAP constraint for all activities. When I try and use the
ASAP constraint on them and then reschedule - it still will not roll the
dates as before. Is there an easy solution?