Hi Frank,
I'm *guessing* that one of the resources assigned has non-working time
in his/her calendar. If you split your screen (Window > Split) to show
the Task Form and then format the Task Form to show Resource Schedule,
there may be a resource who is finishing their work on the task after
all others. You may also see an uneven distribution of work.
For example: In an effort-driven fixed unit task (the default), if I
assign 1 resource at 100% to a 5 day duration task, Project calculates
40 hours of work. The task starts Monday, ends Friday.
Add another resource, total work stays at 40 hours, each resource is
working 20 hours and the duration modifies to 2.5 days. The task starts
Monday and ends mid-day Wednesday.
As I continue to add resources (all with resource calendars which match
the project calendar), duration continues to drop and the 40 hours of
work is evenly divided among the additional resources.
However, if I throw a resource into the mix who has non-working time in
his/her calendar, the process becomes a bit muddled. If I start again
with one resource whose calendar matches the project calendar, again,
same story -- 40 hours of work, 5 day duration, 100% assignment units.
The task starts Monday and ends Friday.
If I add a resource to the task who only works Monday, Wednesday, and
Friday. The task duration drops to 3.5 days, instead of 2.5 days. The
task starts on Monday and ends Friday mid-day. The first resource (with
the non-modified calendar) starts working Monday morning and finishes
his/her work Wednesday mid-day. But the second resource still has 20
hours of work to accomplish but only on Monday, Wednesday, and Friday.
So his/her work finishes mid-day on Friday. It is that second resource
who is driving the finish date of the task.
If I continue to add additional resources, things get even more
interesting. The original two resources are both scheduled to work
11.77 hours but the newly added resource is scheduled to work 16.47
hours. They all now finish their assignment at different hours of
different days. The duration is still being driven by the resource who
finishes last.
--
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
Thanks everyone for taking the time to reply.