R
Rich N
Hi,
I've got a question about multiple resources. I've had a look through the
FAQ and searched through some old posts, but I couldn't find anyone with the
same problem.
I've got two developers and two tasks. Task A (50 hours of work) can only be
done by Bob, but Task B (100 hours of work) can be done by either Bob or
Steve (or both together). I'd like to able to level resources to find the
minimum duration for these tasks, but I'm not sure how to do this.
The solution that I'd like is for Bob to work on Task A until it is
complete, during which time Steve will work on Task B. Once Bob has finished
he can help Steve with the remaining 50 hours of work on Task B, which should
take a further 25 hours.
So the total duration is 75 hours (50 hours with Bob on Task A and Steve on
Task B, 25 hours with both on Task B).
If I assign Bob to Task A and both developers to Task B, then level
resources, then they are assigned as I expect for the first 50 hours, but
Steve then stops work whilst Bob continues to toil on Task B for the next 50
hours. I can resolve the problem by manually redistributing the work on Task
B so Bob does 25 hours and Steve does 75, but I'd like this to happen
automatically. Is this possible?
If anyone can help I'd be grateful.
Thanks,
Rich
I've got a question about multiple resources. I've had a look through the
FAQ and searched through some old posts, but I couldn't find anyone with the
same problem.
I've got two developers and two tasks. Task A (50 hours of work) can only be
done by Bob, but Task B (100 hours of work) can be done by either Bob or
Steve (or both together). I'd like to able to level resources to find the
minimum duration for these tasks, but I'm not sure how to do this.
The solution that I'd like is for Bob to work on Task A until it is
complete, during which time Steve will work on Task B. Once Bob has finished
he can help Steve with the remaining 50 hours of work on Task B, which should
take a further 25 hours.
So the total duration is 75 hours (50 hours with Bob on Task A and Steve on
Task B, 25 hours with both on Task B).
If I assign Bob to Task A and both developers to Task B, then level
resources, then they are assigned as I expect for the first 50 hours, but
Steve then stops work whilst Bob continues to toil on Task B for the next 50
hours. I can resolve the problem by manually redistributing the work on Task
B so Bob does 25 hours and Steve does 75, but I'd like this to happen
automatically. Is this possible?
If anyone can help I'd be grateful.
Thanks,
Rich