P
Philg
I have a resourced project schedule the Gantt view expresses the work (days)
required to deliver the scheduled activities.
The problem I have is after exporting the resource information using analyze
timescale data I’m presented with a different man-day total, this doesn’t
happen for all my schedules but just occasionally for the more complex
schedules with lots of resources.
Has anyone else experienced this problem, I do have a solution but I need to
understand the cause.
any help is appreciated
Phil
required to deliver the scheduled activities.
The problem I have is after exporting the resource information using analyze
timescale data I’m presented with a different man-day total, this doesn’t
happen for all my schedules but just occasionally for the more complex
schedules with lots of resources.
Has anyone else experienced this problem, I do have a solution but I need to
understand the cause.
any help is appreciated
Phil