Analyze Timescale Data and baseline cost allocation issues

V

Verossa

Hello

I have created a number of hammock tasks, task type: fixed work, with single resource allocations. The hammock tasks are linked by start / finish. When I check the monthly task usage the hours are assigned across a flat contour for the duration of the project

However, when using Analyze Timescale Data to view baseline cost, all the costs for the hammock are allocated to the first month and not across subsequent months

What am I doing wrong

Any information would be appreciated

TIA - Vers
 
V

Verossa

Please do not reply

I reallocated one of the tasks and everything seems to be working - very odd

Vers
 
G

Gérard Ducouret

Hello Verossa,
In the Resource Sheet, did you take care of the "Accrue At" field where you
could say that this resource will be paid at the begining of his/her
intervention.

Gérard Ducouret
 