Verossa
Hello
I have created a number of hammock tasks, task type: fixed work, with single resource allocations. The hammock tasks are linked by start / finish. When I check the monthly task usage the hours are assigned across a flat contour for the duration of the project
However, when using Analyze Timescale Data to view baseline cost, all the costs for the hammock are allocated to the first month and not across subsequent months
What am I doing wrong
Any information would be appreciated
TIA - Vers