A
Al
I was working on a task that had different working hours e.g. I had to use a
12 hours a day 7 days a week. When I applied by new 12/7 caledar it
calculated the finish date correctly but it did not change the duration. If
my original duration was 16.88 days using an 8 hours day 5 days per week
calendar, what can I do so MS Project calculate the correct duration which is
11.25 days using the new calendar.
P.S. Like I mentioned before I applied the new calendar and it calculated
the correct Finish the problem is the Duration stays the same in this case it
shows 16.88 days which is misleading. Any help is highly appreciated. Thank
You!
12 hours a day 7 days a week. When I applied by new 12/7 caledar it
calculated the finish date correctly but it did not change the duration. If
my original duration was 16.88 days using an 8 hours day 5 days per week
calendar, what can I do so MS Project calculate the correct duration which is
11.25 days using the new calendar.
P.S. Like I mentioned before I applied the new calendar and it calculated
the correct Finish the problem is the Duration stays the same in this case it
shows 16.88 days which is misleading. Any help is highly appreciated. Thank
You!