I have 4 tasks that will take 1 hour of work. I will assign 4 resources for
that task at 1 hour. All my resources are 100% unit. When I assign the
resources do I need to change 100% units? Not sure what to change it to.
All I know is that I altered the units for each resources to 10% instead of
100% and it's not coming out right. It shouldn't change the day but it's
pushing the project date out 4 days instead of 4 hours. I'm so confused.
How do you schedule an hour of work for 4 resources on one task?