P
Philip
I want to assign 1 week of work to a task that takes 8weeks.
Problem: only two decimals are allowed. When i put 0,125 (1/8) MSproject
converts it automatically to 0,13. Due to this my final workload is to high.
How can I assign the 1 week to the 8 weeks task or insert 0,125 weeks for
each task week?
kindest regards,
Philip
Problem: only two decimals are allowed. When i put 0,125 (1/8) MSproject
converts it automatically to 0,13. Due to this my final workload is to high.
How can I assign the 1 week to the 8 weeks task or insert 0,125 weeks for
each task week?
kindest regards,
Philip