C
Christina
MS Project 2003, PS 2003
We have created individual project schedules to track non-project work for
enterprise resources that tend to be constraints on Corporate projects. That
person's manager is the Project Owner (i.e. Project Manager) and Task
Approval Manager.
Q- Is there a way to designate another person (i.e. Team Lead) to
temporarily be the Task Approval Manager, as well as be able to modify task
assignments as needed? (Without assigning the Lead the Project Manager
permission)
My thought was to assign specific PM permissions to the Team Lead group that
would allow them to create new tasks, re-allocate work, publish, and process
task updates. I'm hesitant to assign them to the PM group since it may
contain permissions that are not appropriate for them to have. However, I
don't know how the RBS comes into play and if the Project Manager field will
"recognize" a person in the Team Lead group as someone who can process task
updates. Or if the Project Owner field will recognize the Team Lead group as
allowed to modify the schedule.
I hope that made sense. Any thoughts?
Thanks!
Christina
We have created individual project schedules to track non-project work for
enterprise resources that tend to be constraints on Corporate projects. That
person's manager is the Project Owner (i.e. Project Manager) and Task
Approval Manager.
Q- Is there a way to designate another person (i.e. Team Lead) to
temporarily be the Task Approval Manager, as well as be able to modify task
assignments as needed? (Without assigning the Lead the Project Manager
permission)
My thought was to assign specific PM permissions to the Team Lead group that
would allow them to create new tasks, re-allocate work, publish, and process
task updates. I'm hesitant to assign them to the PM group since it may
contain permissions that are not appropriate for them to have. However, I
don't know how the RBS comes into play and if the Project Manager field will
"recognize" a person in the Team Lead group as someone who can process task
updates. Or if the Project Owner field will recognize the Team Lead group as
allowed to modify the schedule.
I hope that made sense. Any thoughts?
Thanks!
Christina