Assigning resources to summary task

B

bakulb

Hi,
I am adding resources to summary tasks instead of the
individual tasks in some sections of my WBS. When I go to
task usage view, I see a large number of items in the
unassigned section with no resource assigned. Is this
going to affect the resource usage numbers in any way?

Cheers.
Bakulb
 
J

Jan De Messemaeker

Hi,

You seem to assume that assigning resources to summary tasks is equivalent
to assigning them to the subtasks. RThat is not true. Resources assignend to
a summary task are assigned for the duration of the summary task so when
subtasks overlap or when ther eis a gap between the tasks work is not the
same in both cases.
It is by far preferrable to assign resoruces to tasks.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top