Assigning Resources

A

AlisonH

I have a task (to deliver training) that uses 100% of 3 named resources, and
runs for 59 days. However, one of the nominated trainers will be training on
another task for 10 days in the middle, whilst the other two trainers
continue through. How do I set up the task to cater for this (BTW: The 59
days durn is what it WILL take allowing for the 10 day absence of 1 trainer)?
 