S
SinCity416
Hi,
I have experiencing an issue with Project 2003. here is my situation:
I have 10 dependencies that I need from 1 person on the same day.
I put down the duration as 1 day for each one of them but as soon as I
assign the same resource name to all 10. the dates changes and project
tells me that it will take 10 days for the dependencies to be
completed.
Is there a default setting or something that I can change somewhere so
that whenever I assign the same resource to different task that might
fall under the same timeframe, I don't want project to change the
dates thinking that one person cannot do more than 1 taks on one day.
Thanks.
Amar
I have experiencing an issue with Project 2003. here is my situation:
I have 10 dependencies that I need from 1 person on the same day.
I put down the duration as 1 day for each one of them but as soon as I
assign the same resource name to all 10. the dates changes and project
tells me that it will take 10 days for the dependencies to be
completed.
Is there a default setting or something that I can change somewhere so
that whenever I assign the same resource to different task that might
fall under the same timeframe, I don't want project to change the
dates thinking that one person cannot do more than 1 taks on one day.
Thanks.
Amar