Assignment to more than one Admin Project

M

MartinG

I have read that resources should only be assigned to one admin project -
what is the effect of adding them to more than one? It would be useful for
us to track some aspects of non-project time separatly from others.

MartinG
 
M

Mike Glen

Hi Martin,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP



I have read that resources should only be assigned to one admin
project - what is the effect of adding them to more than one? It
would be useful for us to track some aspects of non-project time
separatly from others.

MartinGHi ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.
 
D

Dale Howard [MVP]

MartinG --

You can assign resources to multiple administrative projects if that is
appropriate. The only consequence of which I can think is that resources
can never hide administrative tasks on their timesheets in PWA, which will
make the timesheet cumbersome if you add them to too many administrative
projects. Hope this helps.
 