I have used the import wizard to map a column of "no. of
resources required" to the assignment units column, but
nothing is shown. Can I do this?
 
J

Jan De Messemaeker

Hi Darc,

You are probably using a task map, and assignment units isn't a task
property.
You could try to import ResourceNames which has the possibility to add the
units between square brackets.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional