auto-balance overallocate and underallocate?

F

Fei

during a project period some of days I am over allocated and some days I am
under allocated. Is there a feature in MSP 2007 that I can use to
automatically workout the overallocated time and fill them in the
underallocated days within the same duration?
e.g. I work 7.5 hours/day, 5 days/wk. on Monday and Tuesday I am
overallocated with a total of 10 hours/day. Rest of the week I am
underallocated with only 3 hours/day. I want to fix the overallocated days by
moving the extra time into the underallocated days which is Wed,Thur and
Friday
 
J

Jan De Messemaeker

Hi,

No feature in Project moves "time", only assignments.
How does this over/underallocation come about?
By many small tasks or as a copntour of one task?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 