S
Steve Scott
Situation:
I have a 100 days of Business Analyst (BA) resource in January and 120 days
in Febuary.
January has 20 working days in it and February 19 working days. In order to
understand the BA resource's availability for Jan and Feb, I have divided
100 by 20 and 120 by 19 respectively. This gives me Monthly % availibilities
of 500% and 632% respectively.
I am now creating tasks and BA assigments within January and February in
order to see if I exceed the monthly % availibilities...
Question - what bearing if at all does the Days per month figure in
Tools/Options have on what I am doing?
I have a 100 days of Business Analyst (BA) resource in January and 120 days
in Febuary.
January has 20 working days in it and February 19 working days. In order to
understand the BA resource's availability for Jan and Feb, I have divided
100 by 20 and 120 by 19 respectively. This gives me Monthly % availibilities
of 500% and 632% respectively.
I am now creating tasks and BA assigments within January and February in
order to see if I exceed the monthly % availibilities...
Question - what bearing if at all does the Days per month figure in
Tools/Options have on what I am doing?