Hi Robert,
Running Project 2007 Professional SP-1 I see the following:
Resource Availability set on Resource Information dialog box:
Available From: 1/1/08
Available to: 7/31/08
Max. Units 100%
When viewed in the Resource Usage view with a system date of today:
Available from: 8/1/08 12:00 am
Available to: NA
Max. Units 0%
This makes perfect sense. After 7/31/08 at 11:59 pm the resource's
availability is zero because I haven't entered any other entry in
the
Resource Information dialog box.
If I edit the resource availability and add a second row:
Available from: 8/1/08
Available to: [No entry]
Max. Units 50%
Viewed in the Resource Sheet:
Available from: 8/18/08 12:00 am
Available to: NA
Max. Units 50%
Because I have not entered a date in the Available to: field it
reads
NA when viewed in both places.
If I edit the second line to:
Available from: 8/1/08
Available to 8/31/08
Max. Units: 50 %
The same data including the available to date of 8/31/08 11:59 pm
shows in the Resource Sheet.
So, in short, Jan was correct. The information displayed in the
Resource sheet is the information relative to the current date.
For the resources who have left the company their max. units should
be
zero currently. Remember, you can still assign resources who have
zero max units -- it will just overallocate them.
You can use the Assign Resources dialog box to replace the
resources
who have left the company with the new resources. Project will
maintain any actual work data on tasks where there is tracked work
with the resource who has left and assign any remaining work to the
new resource.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
Robert said:
No resolution yet. Can anyone offer any suggestions. Project
Server is not
involved.
Thanks,
Robert
:
In Proj Prof 2007, these fields on the General tab of the
Resource
Information dialog box seem inconsistant with the Available To
and
Available
From resource fields when displayed in a Resource view.
The DAY FOLLOWING the value of the Available To field in the
Resource dialog
box is overwriting the Available From field in a Resource view.
Both fields appear to be read only in Resource views. The
Available To
field in a Resource view never populates.
What's wrong?