User Defined Fields - MSP 2003

J

JKR

Is it possible to have the same configuration setup on user defined fields as
is available on system defined fields? Our issue: we would like to define a
field at the task level ("Estimated Hours") for tasks and make this field
available on the resource records for resources assigned to the task. We
want to create a view (resources) and have the "Estimated Hours" roll up to a
higher RBS level. The goal is to see how many hours have been estimated for
tasks for a particular level of the RBS. We haven't been able to get the new
user defined field to be visible in the "resource" area when creating a new
view, it is available in the "task" area however. We have noticed that
"Actual Work" is a field available in both the resource and task areas. Any
help with this is appreciated. Thanks.
 
J

JKR

Thanks for the info Trevor. "RBS" is the Resource Breakdown Structure - the
user defined hierarchy to group resources by organizational structure. Any
thoughts on another approach to accomplish our goal?
 