M
MAT
Hi
As you know, the PMs can save anytime the baseline. It is ofcource important
that the PM saves the basline befor publishing the project and do not make
anychange if is is not necessary, so that the directors can check everything
(for examle with portfolioanalyser)
I noticed that some of our PMs reflesh the baseline althought it is not
necessary. Because of that we see as if everthing is always OK.
So I want to avoid that the PMs save the baseline more times. I mean They
should do it jsut one time in the phase of planning. and after publishing
they should not do this again..
Is that possible?
Thanks.
As you know, the PMs can save anytime the baseline. It is ofcource important
that the PM saves the basline befor publishing the project and do not make
anychange if is is not necessary, so that the directors can check everything
(for examle with portfolioanalyser)
I noticed that some of our PMs reflesh the baseline althought it is not
necessary. Because of that we see as if everthing is always OK.
So I want to avoid that the PMs save the baseline more times. I mean They
should do it jsut one time in the phase of planning. and after publishing
they should not do this again..
Is that possible?
Thanks.