randluke
II am adding change request to a project I have baselined. I am baselining
the change request and roll it up under the summary. Will the dependencies
that appear under a different summary task change as well.
OR will the change request and the summary task only change their baseline
dates? (This seems to be what is happening)
the change request and roll it up under the summary. Will the dependencies
that appear under a different summary task change as well.
OR will the change request and the summary task only change their baseline
dates? (This seems to be what is happening)