How to see multiple Baseline gantt in Tracking View in
Project Prfessional ? Out of 11 Baseline start & finish
dates, which one is used to compare ? Is it the lat
updated one or oldest one ? How to compare the present
paln with mutliple basleines ?

Regards

Sriram
 
R

Rod Gill

Hi,

The tracking Gantt uses the Baseline. To see Baseline1 to 10 you need to
select Format, Bar styles and either change the baseline bar to show
Baseline1..10 or add a new bar.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 