Baseline comparison

J

Jamie

I have a baseline saved and I've added tasks after. Is there way to generate
a report that would show me the tasks I've added after I've saved my baseline?
 
D

DavidC

Hi Jamie,

First you need to filter out any task that does not have a baseline set. A
simple way is to filter out any task that does not have a value in the
"Baseline Start" field. Use the criteria "equals" and the value is then
"NA". You can then write a custome report using this filter as the filter
criteria.

Hope this helps

Regards

DavidC
 
R

Rod Gill

Make sure that you date stamp the copy and leave the master name unchanged.
That way any Hyperlinks to your file continue to work.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 