Thank you for this thread. Everything you say makes perfect sense.
Actually, I've been comparing Finish variances for successive interim
plans
(not baselines), to see if the variances are decreasing with time. My
assumption: if variances decrease it's because estimating is
improving, and
I'll have good effort factors for the next project. In fact, the
Finish
variances are not decreasing, so I know to use this historical data
with
caution. What do you think of this logic?
:
There's nothing wrong with the length of the projects and I can't
think of
any reason why shorter would be preferrable - even longer projects
are far
from uncommon. 12 to 18 month long individual TASKS, on the other
hand,
would be another story.
It depends on whether the project schedule is changing or the project
itself
is changing. IMHO, actual progress always be compared to the
original
schedule even if the estimated schedule has changed in the meantime.
Task A
may have been estimated at 30 days so B would have started 01 Sep but
now it
appears that A will take 45 days and the schedule has changed with B
now
starting on 21 Sep - that sort of change should not prompt a new
baseline.
Only if the project scope itself is changing - new features added or
features dropped on a program in development, for example - should it
be
rebaselined. But if the changes are simply that the estimates of
duration,
required work, etc have changed or are more precise or there have
been
changes in resource availability should not trigger a new baseline.
In
fact, tracking against your original estimates gives you good
historical
data so you can refine your estimating processes for the next
project.
Just one opinion, YMMV
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
We have projects that last 12-18 months (yes, shorter projects are
preferable). Precision of estimates for downstream tasks improves,
tasks
are
added and dropped, etc. Projects change substantially, so we
re-baseline
every 5-7 months.
:
Why do you keep saving and overwriting baselines? The baseline
represents
the plan you intend to work. It should not be overwritten as the
project
progresses EXCEPT when new tasks are added and/or tasks deleted
because
the
desired outcome has changed and so it essentially becomes a new,
different,
project. The fact that a plan does not progress exactly as
originally
scheduled does not mean the baseline would change - you should
always be
tracking progress against your original plan. IMHO, the ability
to save
multiple baselines in mainly of use to retain an audit trail of
the last
series of changes to the plan as it's polished prior to beginning
work or
to
provide for the possiblity that a project may have several
possible
outcomes
and which one it will go for hasn't been decided prior to work
commencing
(ie, perhaps the first major phase is a feasibility study and at
its
conclusion you decide which product goes into production).
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I had the same problem, and came up with this workaround:
When I save the first baseline, I save it twice, (or copy it
right
after I
save one)once to Baseline, once to Baseline1. Both then have
the first
baseline date (say 5/1)
Then when I save the next baseline, I can save it to Baseline
and
Baseline2.
Both of these will have the new baseline date (say 6/15). I
repeat
that
for
each baseline I save, so that Baseline then always has my most
current
version and it has its clone with the same date, so it would
look
something
like:
Baseline (saved 8/2)
Baseline1 (saved 5/1)
Baseline2 (saved 6/15)
Baseline3 (saved 8/2)
- Sue
:
In Baseline0 I have a baseline dated 9/7/05. When I copy
Baseline0 to
Baseline1, how can I make the copy keep the original date
stamp?