Baseline Dates in Group View

G

Gérard Ducouret

Hi Pam,
I'm not sure i understand well what you want, but I'ld try:
Format / Bar Styles...
Scroll down to the "Group By Summary" bar,
Click the Text tab
Left or Right : select Baseline Start...

Hope this helps,

Gérard Ducouret
 
J

John

Pam said:
Is there a way to show the baseline dates on a Group Summary in the Gantt
Chart?

Pam,
Unfortunately, no. Grouping in Project creates artificial "groups" of
selected tasks for viewing purposes only. Many of the normal fields
(including baseline fields) are simply not available or valid at the
Group Summary level.

John
 