Baseline Work Total in Resource Usage View

E

Ed Ryan - Wrigley

I would like to see the baseline work total for each resource in the resource
usage view. Currently, I am only seeing the baseline work for each task
under each resource... and the Baseline work total is blank. Is it
possible to have a total?
 
J

John

Ed Ryan - Wrigley said:
I would like to see the baseline work total for each resource in the resource
usage view. Currently, I am only seeing the baseline work for each task
under each resource... and the Baseline work total is blank. Is it
possible to have a total?

Ed,
I don't have Project open at the moment but as I recall this was a
problem with Project 2000 and maybe with Project 2003 before updates
were installed. Make sure you have the latest updates installed for
whatever version of Project you are using.

John
Project MVP
 
F

Fei

I have the same issue.
Environment:
1. project 2007,
2. Vista Enterprise x64
3. enterprise project server
 