project newby said:
Hi there,
I am trying to learn how to use baselines (and what they are good for).
I set up a simple programme and saved the project baseline as baseline
1. I then rescheduled one task on the critical path such that the whole
programme was shifted a little. How do I represent this shift using
baselines?
Many thanks,
DE
DE,
No need to post twice, we got it the first time.
Baseline data in Project is a snapshot of the plan at some point in time
- normally at the beginning just before plan execution starts. The
purpose of a baseline is to provide a point for measuring performance,
most often using earned value metrics. For example, as the plan is
executed, the current schedule (i.e. task start, task finish, duration,
etc.) change due to the dynamics of real life. By using the stored
baseline data, the project manager can measure how performance compares
to the original plan (i.e. ahead or behind).
Ideally, only one baseline is set and that is at the beginning. In my
opinion it is unfortunate that Project provides for multiple baselines
because it gives many users the impression that it is OK to set a new
baseline every time things start to go "South". To be fair, there are
circumstances wherein a selective reset of the baseline is appropriate.
For example, a change in scope, tasks are added, etc.
If you had to reschedule a task, one way to use the baseline data is to
look at the Start or Finish Variance fields. They will tell you how many
days that task was shifted from it's original schedule.
Hope this helps.
John
Project MVP