Copying Baselines in Project 2007

J

JohnW

Is there a way to copy baselines (or portions thereof) in Project 2007? For
example, have saved the current plan into baseline1, at a later time can I
copy baseline 1 to baseline 2?
 
J

JohnW

Does his copy the "entire" baseline (for the selected tasks)? The
documentation gave me the imression that interim plans were a subset of a
full baseline - I was concerned that I'd only get some of the baseline
data...
 
J

JohnW

Thanks! I guess the fact that the option was in the "Set Interim Plan"
section that threw me...
 