Baselines

  • Thread starter % Complete vs Actual Work
  • Start date
%

% Complete vs Actual Work

What is the number of baselines I can maintain in project and how they get
used up with each new baseline that is saved... e.g. do you use up one of the
10 baselines each time you baseline a different sub section.
 
J

JulieS

Hi ???

In releases after Project 2000, you may have a total of 11 baselines
(Baseline plus Baseline1 through Baseline10).

You do not overwrite baseline data for selected tasks when you baseline
other selected tasks.

For example: Select tasks 1 through 10 and saved to Baseline1. Then
select tasks 11 through 20 and saved to Baseline1. The baseline1 data
for tasks 1 through 10 is not changed -- only the new baseline1 data for
tasks 2 -20 is saved.

You can add additional baseline fields (Baseline Start1, Baseline Cost1,
BaselineCost2, etc) to view the various baseline fields.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"% Complete vs Actual Work"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top