BCWP Calculation

J

Jim Aksel

I have a baselined task and a resource assigned to work that task at rate
$A/hr.
Work starts and the task starts running behind schedule. In the meantime,
management states new rates are to be used -- $B/hr.

Changing rates is an acceptable reason to re-baseline this activity by our
business rules. The question is -- after the new rate takes effect, I
believe I will earn EV (BCWP) at the new rate for the remainder of this
activity, correct??

That is, once I re-baseline this task, I have changed its value by
($A/hr-$B/hr)*(Remaining Work). So my revised EAC should refelct only the
change and new dates?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top