S
Steve Schacher
A question came up from one of my co-workers. Is it true that the BCWP
only calculates up to the status date?
I was playing around with baselines, status dates, and percent
complete, and could never get the BCWP to be greater than the BCWS
until I either started a task earlier than baseline or completed the
task ahead of baseline. Incomplete tasks that are ahead of schedule
don't seem to work the way I expected, i.e., BCWP always equals BCWS,
and SPI is always 1.
How do you use BCWS, BCWP, & SPI on tasks that are ahead of schedule
but not complete yet?
Steve Schacher
only calculates up to the status date?
I was playing around with baselines, status dates, and percent
complete, and could never get the BCWP to be greater than the BCWS
until I either started a task earlier than baseline or completed the
task ahead of baseline. Incomplete tasks that are ahead of schedule
don't seem to work the way I expected, i.e., BCWP always equals BCWS,
and SPI is always 1.
How do you use BCWS, BCWP, & SPI on tasks that are ahead of schedule
but not complete yet?
Steve Schacher