Begin times?

Z

zootboot

I remember in previous versions of Project being able to insert a column with
the time values rather than days. Does anyone know how to change the values
of the start column to enter time of day rather than date?
 
J

JulieS

Hi Zootboot,

To view the dates and times of your tasks go to Tools > Options > View tab.
Change the date format to show date and time.

Please note, it is not recommended to manually enter dates in either the
Start or Finish column. Entering in Start or Finish dates sets constraints
on the task.

Hope this helps. Let us know how you get along.

Julie
 