I lead a PMO using Server 2003 and time reporting via PWA from the project
resources. We teach the PMs to take the updates from the team members and do
the "Update" function (in PWA) and then to set the status date and do the
"Update Project" function in Project Pro. After doing this, we have them
"Publish", "New and Changed Assignments".
The problem is that the black line that shows project completion in the
Project Center will not advance unless the PMs "Publish" "All Information"
rather than just New and Changed Assignments. Shouldn't it advance under any
Publish scenario?
texasroy
resources. We teach the PMs to take the updates from the team members and do
the "Update" function (in PWA) and then to set the status date and do the
"Update Project" function in Project Pro. After doing this, we have them
"Publish", "New and Changed Assignments".
The problem is that the black line that shows project completion in the
Project Center will not advance unless the PMs "Publish" "All Information"
rather than just New and Changed Assignments. Shouldn't it advance under any
Publish scenario?