T
texasroy
We have several projects that do not seem to show the progress (Black Line)
properly in the Project Center. One project was properly updated (took
updates from resources and Accepted and Updated them in PWA and then went to
Project Pro, set the status date and performed the Tracking, Update Project,
Schedule uncompleted work to start after functions. For most of our projects
this works fine, but a few of them the line does not fully progress. One
project shows progress through May 23 even though inputs were accepted and
progress statused as of June 10. Any ideas?
Roy Pool PMO Lead
properly in the Project Center. One project was properly updated (took
updates from resources and Accepted and Updated them in PWA and then went to
Project Pro, set the status date and performed the Tracking, Update Project,
Schedule uncompleted work to start after functions. For most of our projects
this works fine, but a few of them the line does not fully progress. One
project shows progress through May 23 even though inputs were accepted and
progress statused as of June 10. Any ideas?
Roy Pool PMO Lead