S
Steve Scott
I have approx 2000 tasks which are all 3months fixed duration. I need to be
able to assign monthly work eg 10 days in Oct; 5 days in Nov, 2 Days in Dec.
I have the monthly work data in a spreadsheet/access db. How can I
automatically upload the work spread rather than just allowing project to
spread the 17 days across the 3months itself? I cannot go into each task and
do this manually as it would take forever.
Thanks
able to assign monthly work eg 10 days in Oct; 5 days in Nov, 2 Days in Dec.
I have the monthly work data in a spreadsheet/access db. How can I
automatically upload the work spread rather than just allowing project to
spread the 17 days across the 3months itself? I cannot go into each task and
do this manually as it would take forever.
Thanks