A
acbeale
Hi,
What I want to see in my project plan is a task bar that reflects the
following type of statement: This task represents 2 days work, done over
a fixed 10 day period.
ie, I want to define a task bar of 10days fixed duration but where the
amount of work done over that 10 days is only in fact 2 days work (ie
the work would be spread evenly or unevenly over the 10 days, but the
work would be done by the end of the 10 days).
Now, I know I can assign a resource and then use the UNITS for that
resource to do this, BUT that gets really ugly when, say, you have an
example like a fixed duration of 31 days, in which 1.5 days work must be
done. I simply want to input those 2 numbers somewhere (31 and 1.5), I
don't want to have to calculate and use trial-and-error to figure out
the units value that would give me the equivalent answer.
Is that possible?
Thanks, Andrew Beale
London
What I want to see in my project plan is a task bar that reflects the
following type of statement: This task represents 2 days work, done over
a fixed 10 day period.
ie, I want to define a task bar of 10days fixed duration but where the
amount of work done over that 10 days is only in fact 2 days work (ie
the work would be spread evenly or unevenly over the 10 days, but the
work would be done by the end of the 10 days).
Now, I know I can assign a resource and then use the UNITS for that
resource to do this, BUT that gets really ugly when, say, you have an
example like a fixed duration of 31 days, in which 1.5 days work must be
done. I simply want to input those 2 numbers somewhere (31 and 1.5), I
don't want to have to calculate and use trial-and-error to figure out
the units value that would give me the equivalent answer.
Is that possible?
Thanks, Andrew Beale
London