M
Markarina
Based on what I have learnt from this forum I was hoping the following
would work:-
I have a resource that only works two days a week on a project (Monday/
Tuesday) so I've set max units to 40% (5-day working week) and set the
resources calendar so that working hours are 8 hours Monday and 8
hours Tuesday. What I was hoping was that when I assigned the resource
to a 16 hour (work) task the duration would be calculated to be 2
days. However the results given by MSP 2007 are somewhat strange.
Duration is calculated as 5 days and the actual period over which the
work is done is 15 days. It looks like project has made the assumption
that the resource can only work 40% of each day rather than 40% of
each week. Likewise a resource with 40% units but who works 5 days a
week will still have a duration of 5 days.
Trying to answer my own question it looks like project applies the max
units on a per day basis rather than a per week basis, so if you have
a resource that is only available to work on a project 2 days per week
but these days can vary their is no simple way for project to take
this into account given that it applies max units on a per day basis
and not a per week basis.
would work:-
I have a resource that only works two days a week on a project (Monday/
Tuesday) so I've set max units to 40% (5-day working week) and set the
resources calendar so that working hours are 8 hours Monday and 8
hours Tuesday. What I was hoping was that when I assigned the resource
to a 16 hour (work) task the duration would be calculated to be 2
days. However the results given by MSP 2007 are somewhat strange.
Duration is calculated as 5 days and the actual period over which the
work is done is 15 days. It looks like project has made the assumption
that the resource can only work 40% of each day rather than 40% of
each week. Likewise a resource with 40% units but who works 5 days a
week will still have a duration of 5 days.
Trying to answer my own question it looks like project applies the max
units on a per day basis rather than a per week basis, so if you have
a resource that is only available to work on a project 2 days per week
but these days can vary their is no simple way for project to take
this into account given that it applies max units on a per day basis
and not a per week basis.