Calculated custom field values does not update in project web acce

E

ejavier

I created an enterprise custom field (number) to display "% planned
completion" using a formula that displays 100 if baseline finish is less than
current date, 0 if baseline start is greater than current date, and the
percentage of days lapsed over baseline duration. I included this field in a
view in the project web access. The formula works and the values are correct
once published but values in the Project Web Access are not updated
automatically. Is there a setting that will allow automatic recalculation in
the project web access?
 
M

Mike Glen

Hi ejavier ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top