R
Rob
I have project 2007 pro-not using server.
I have used the formula from John below to get an expected/scheduled %
complete calculation but get #ERROR in Text1 Field for Milestones.
Any Ideas?
Thanks for your help.
*****
It will just take 3 custom fields instead of one. Here's the
basic outline of the process.
1. Create three custom fields (e.g. Text1, Duration1, and Duration2)
2. At the task level use the following formulas:
Text1=IIf([Duration1]/[Duration2]>=1,"100%",IIf([Duration1]/[Duration2]=0
,0,format([Duration1]/[Duration2],"#.00%")))
Duration1=IIf(projdatediff([Baseline Start],[Date1])>[Baseline
Duration],[Baseline Duration],IIf(projdatediff([Baseline
Start],[Date1])<=0,0,projdatediff([Baseline Start],[Date1])))
Duration2=[Baseline Duration]
3. At the summary level use "rollup - sum" for Duration1 & Duration2
4. At the summary level "use formula" for Text1
John
Project MVP
*****
I have used the formula from John below to get an expected/scheduled %
complete calculation but get #ERROR in Text1 Field for Milestones.
Any Ideas?
Thanks for your help.
*****
It will just take 3 custom fields instead of one. Here's the
basic outline of the process.
1. Create three custom fields (e.g. Text1, Duration1, and Duration2)
2. At the task level use the following formulas:
Text1=IIf([Duration1]/[Duration2]>=1,"100%",IIf([Duration1]/[Duration2]=0
,0,format([Duration1]/[Duration2],"#.00%")))
Duration1=IIf(projdatediff([Baseline Start],[Date1])>[Baseline
Duration],[Baseline Duration],IIf(projdatediff([Baseline
Start],[Date1])<=0,0,projdatediff([Baseline Start],[Date1])))
Duration2=[Baseline Duration]
3. At the summary level use "rollup - sum" for Duration1 & Duration2
4. At the summary level "use formula" for Text1
John
Project MVP
*****