E
Emily
Hello,
I have noticed something in a plan, that I believe is not performing the way
I would expect.
I am using MS Project 2002.
I have a task, which is Fixed Duration, that has a single resource assigned
to it. This resource, for sake of scenario, has a Std. Rate of $1.00/hour.
The task has a duration of 5 days, which works out to be 20 hours or 4 hours
a day.
I recorded the task as 50% complete and I expected that the Actual Cost to
be $10 hours and the Actual Work to be 10 hours. In fact, I noticed that the
Actual Work and the Actual Cost remained 0h and $0 respectively.
I tested out such a scenario on a new plan, and as I expected, the Actual
Cost and Actual Work responded as expected.
I am not sure if there is a setting in my plan that would prevent the Actual
Cost / Work from changing, but if there is any help, I would greatly
appreciate it.
Thanks,
Emily
I have noticed something in a plan, that I believe is not performing the way
I would expect.
I am using MS Project 2002.
I have a task, which is Fixed Duration, that has a single resource assigned
to it. This resource, for sake of scenario, has a Std. Rate of $1.00/hour.
The task has a duration of 5 days, which works out to be 20 hours or 4 hours
a day.
I recorded the task as 50% complete and I expected that the Actual Cost to
be $10 hours and the Actual Work to be 10 hours. In fact, I noticed that the
Actual Work and the Actual Cost remained 0h and $0 respectively.
I tested out such a scenario on a new plan, and as I expected, the Actual
Cost and Actual Work responded as expected.
I am not sure if there is a setting in my plan that would prevent the Actual
Cost / Work from changing, but if there is any help, I would greatly
appreciate it.
Thanks,
Emily