Calculating the CPI and SPI

M

martin.champoux

Hello,

I calculated the CPI and SPI on my project. The CPI is 1.20 and SPI is
0.30.

Can I really observe the SPI and CPI when I know that a lot of task
started with X workers but the number of workers will increase by 2 or
3 when we will be at the peak of the task. THe task has about 1500 days
of work for 300 days of elapse.

The project is not late so is the data wrong ?

Thanks
Martin
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top