Yes. However, CPI will always be 1.0 if you are not careful.
To work around that:
Select Tools/Options, pull the calculations tab.
UNcheck the box "Actual costs are always calculated by Microsoft Office
Project"
check the box "Edits to total actual cost will be spread to the status date"
Default fixed costs accrual - select what is meaningful, probably prorated.
Now, when you baseline the project you can use %Complete for calculations of
SPI & CPI.
CPI will always be 1.0 .... unless you enter a different value in the
[Actual Cost] column.
Examples: A purchased item was less expensive than your baseline fixed
cost, or, a resource more expensive than your baseline bid was used on the
poject.
Use of fixed costs (CPI=1 always) is not a bad way to go if you have a fixed
price subcontracted effort for a task.
So, enter your fixed cost in the Fixed Cost Column -- if things run
differently, override that value with an entry in the [Actual Cost] column.
Hope that helps, if so please consider rating this response.
Jim
Will Project calculate CPI and SPI if I enter the "fixed cost' for all
my activities, baseline the project and update the plan accordingly
with percent complete?
Thx.