T
ttorneby
I'm having huge problems finishing a plan I'm working on. Maybe someone
here has some clever ideas.
To take it from the beginning: This is a part of some school work, and I
have a number of tasks, and for each of the tasks I have details on what
the budget is, and the planned duration. At a specific point in time I
have details on the completion rate of each task, as well as the money
spent, and the actual duration. From these figures, I want MS Project to
calculate figures such as BCWS, ACWP, BCWP, EAC, SPI and CPI.
My problem is that I have not found a place to enter the budget cost for
each task, without having to assign resources and all this. I've only
found two coloums containing the word "budget", but neither of them
allows me to enter values. Is there not a simple way to do this?
Also, it seems like "actual duration" and "% work completed follow each
other. F.ex. on a specific task, 13 out of 16 weeks are spent, but the
work is only 75% completed. MS Project doesn't seem to accept this.
I've attached a screeshot of what I'm working on, in case it might be at
help.
Any help on this matter is highly appreciated!
+-------------------------------------------------------------------+
|Filename: screenshot.png |
|Download: http://forums.techarena.in/attachment.php?attachmentid=11002|
+-------------------------------------------------------------------+
here has some clever ideas.
To take it from the beginning: This is a part of some school work, and I
have a number of tasks, and for each of the tasks I have details on what
the budget is, and the planned duration. At a specific point in time I
have details on the completion rate of each task, as well as the money
spent, and the actual duration. From these figures, I want MS Project to
calculate figures such as BCWS, ACWP, BCWP, EAC, SPI and CPI.
My problem is that I have not found a place to enter the budget cost for
each task, without having to assign resources and all this. I've only
found two coloums containing the word "budget", but neither of them
allows me to enter values. Is there not a simple way to do this?
Also, it seems like "actual duration" and "% work completed follow each
other. F.ex. on a specific task, 13 out of 16 weeks are spent, but the
work is only 75% completed. MS Project doesn't seem to accept this.
I've attached a screeshot of what I'm working on, in case it might be at
help.
Any help on this matter is highly appreciated!
+-------------------------------------------------------------------+
|Filename: screenshot.png |
|Download: http://forums.techarena.in/attachment.php?attachmentid=11002|
+-------------------------------------------------------------------+