Calculating Time

B

BB

What is the correct formula to use in a custom field in order to take a start
time from one field and add 30 minutes to it?
 
J

JulieS

Hi BB,

Try:

ProjDateAdd([Start],30) in a date field (for example Date1).

I hope this helps. Let us know how you get along.

Julie
 
B

BB

Works great. Thank-you, Thank-you Thank-you.

JulieS said:
Hi BB,

Try:

ProjDateAdd([Start],30) in a date field (for example Date1).

I hope this helps. Let us know how you get along.

Julie

BB said:
What is the correct formula to use in a custom field in order to take
a start
time from one field and add 30 minutes to it?
 
J

JulieS

Hi BB,

Glad to have helped and thanks for the feedback.

Julie

BB said:
Works great. Thank-you, Thank-you Thank-you.

JulieS said:
Hi BB,

Try:

ProjDateAdd([Start],30) in a date field (for example Date1).

I hope this helps. Let us know how you get along.

Julie

BB said:
What is the correct formula to use in a custom field in order to
take
a start
time from one field and add 30 minutes to it?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top