Calculation resource utilization / assignement (%)

A

Atle

Hello,

Please consider the following:

One task is set to work for 20 hrs. The duration is set for 2 weeks (80
hrs). How can I calculate how many % (answer: 25%) of this resource's time
will be spent on this task over the 2 week period ?

Thanks a lot!
 
J

Jan De Messemaeker

Hi,

Why would you calculate that? Project does it for you.
Assign the resource to the task
Gantt Chart, Window menu, Split
In the foem below
set task type to fixed duration
fill in the right diuration
fillin the amount of work
Click OK
HTH
 
M

Mike Glen

Hi Atle,

Also, you might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly the principles in #10 on resource assignments,
at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 